M&T Shop Building: Raising the Bents Day Two


 

This morning the crew gathered at 7:00 and devised a plan for raising the next three bents. The members between the bents are connected to each other with a 24’ long joist and so they were assembled as a unit and raised into place with a manual lift. The next bent was assembled on horses on the ground and carried into place by Matt via telehandler. This process continued all the way through to the fourth and final bent. Happily, there is little to report on because everything went so smooth. Even the twist in the joist between bent two and three was easily pulled into proper alignment.

By the end of the day, we had all four bents assembled. Tomorrow, we plan to put a temporary deck on the second floor and install the 26’ long plates with their braces onto the eave walls. With the plate in place, we can finish pegging the bents together and release the come alongs. After that it’s rafters and ridge pole! We’ll see how far we get tomorrow.

Tonight we feast and then rest before the next exciting step!

- Joshua

 


Would you like email notifications of our daily blog posts? Sign up below...